The second phase of repairs to Exmouth's sea defences is due to begin in late September.
A further 150 metres of vulnerable seawall will be secured with a steel sheet pile wall.
Phase two is expected to cost £1.627million of the estimated full project cost of £3.312million. East Devon District Council (EDDC) has allocated £1.5million to the work, with £1.72million of additional funding from central government.
Since March 2024, engineers have been working hard to put in place permanent measures strengthening Exmouth’s sea defences. A steel sheet pile wall has been installed through the ground and the 90 metres of failed wall, through the nearly completed first phase. This section is where sand levels had dropped below the foundations, causing the wall to fall forward and crack.
After a serious failure to the seawall in 2023, EDDC with its contractors took immediate action with emergency temporary measures to protect the damaged wall. Thousands of tons of sand were transferred, and large concrete blocks were put in place only hours before an impending storm. These temporary barriers successfully absorbed the energy of the waves and prevented further much more serious damage. Following the storm, contractors raised sand levels by the seawall and put additional concrete blocks in place.
On-site engineering work has not been scheduled to take place during the school holidays, to minimise disruption to beachgoers during the busiest periods. In the first phase, contractors have been working on Saturdays too, to complete the project more quickly.
Andrew Hancock, EDDC’s Assistant Director for Streetscene, said: "Strengthening Exmouth’s coastal defences for the next 100 years is vital, with increasingly frequent, more severe storms an unfortunate consequence of the climate crisis.
“Securing the seawall ahead of the winter storm season is an urgent task. The council’s engineers are working incredibly hard to ensure the best options are chosen in terms of financial costs and environmental impacts too.
“EDDC would like to thank visitors, residents, and local businesses for their patience whilst this important work continues."
Phase two was agreed by EDDC’s cabinet on Wednesday, 5 June 2024. Cabinet also considered historic decisions and reasons why the seawall failed, an issue that will be investigated further by a future Scrutiny committee.
Residents will be consulted on the appearance of the wall. The cladding of the wall and the replacement of a slipway (with full planning permission to be requested in due course), will be the focus of the third phase.